NS Gurus,
A Workflow field Field A is set to 0 before State A, and is set to 1 inside State B.
I have a State A transitioning to State B on delay schedule for 1 hour when Field A is 0. State B immediately transition back to State A. This is working perfectly fine no issues and field A is properly set.
Now I have State A transitioning to State C on delay schedule for 1 hour when Field A is 1. Now the Field A is True and Worklog states the transition is executed, but it gets struck in State A. It really doesn’t get into State C And on top of this, because of Delay Schedule AND condition set, it says State C transition is executed every one hour continously!
Am I missing anything? Please advise.
Thank you,
Sree