This topic contains 1 reply, has 0 voices, and was last updated by Patrick Paguia 13 years, 4 months ago.

  • Author
    Posts
  • #7976

    lnanji

    Does anyone know how to add columns to the budget. vs actual report that are individual monthly budgets.

    So instead of the current: Amount, Budget Amount, Amount over budget, % of budget.

    I’d like: Amount (july), Budget amount (july), Amount (August), Budget Amount (July), Amount (Sept), Budget amount (sept)…. etc

    Thanks,

    LN
    This is a cached copy. Click here to see the original post.

  • #7977

    Patrick Paguia

    You can use the Alterante Period Range type feature on the Budget vs. Actual Finacial Report Builder.

    On the Edit Columns link, select the ff field for each column:

    Budget>Amount

    Financial> Amount

    For each column, select the Alternate Period Range type as either Relative to Report Date and then select on the available period ranges. If these period ranges is not within your scope, then select Relative to Today’s date as the Alternate Period Range Type and select Custom on the Alternate Period Range. You can then now opt to select all the available period that you need to.

    You need to do this for all the needed months (period). You also need to create a formula field for each of your budgeted and actual amounts per month. Of course, you need to fill in Column Label to indicate the Months Name (Ex. Actual July 2011, Budget July 2011).